Board of Education » Referendum Updates

Referendum Updates

Over the summer several updates will be completed to both Frederic School District Buildings.
 
Over the last 30 days:
The elementary office was completed.
Sidewalks around the office were poured.
The landscaping surrounding the office was completed.
Interior demolition of learning spaces and old office continued.
Learning spaces were painted and flooring was installed.
New energy-efficient LED lighting was installed in learning spaces.
Started 6-12 school office renovations.
Technical education room interior walls were demolished and new walls were erected. 
Demolition began in the elementary food service area. 
 
In the next 30 days:
Learning spaces are scheduled to be completed.
Renovation of Roots and Branches is scheduled to be completed.
Elementary student services renovation will continue. 
Renovations of the elementary food service area will continue. 
Renovations will continue in the 6-12 office.
Technical education room renovations will continue. 
Cleaning on touch-ups will begin on finished spaces. 
Mechanical units will be delivered and installed.